Case Study : Simonstown East Dockyard

Size: 65800 m2 | Client: DPW


Energy Audit done : Energy Auditing by SEM
Implementation done : Installation by SEM
Contract Type: Shared Savings contract


Project Details

  • Commencement of audit: 1998
  • Completion of installation: 1998
  • End of Shared Savings contract: March 2009

Savings & Interventions

Energy Rand Savings: 
Energy Consumption Savings: 42%
Energy Demand Savings: 26%

Energy Interventions:
  • Co-generation utilising existing alternator
  • Power Factor Correction
  • Ripple control system (central max. demand control)
  • A/C operating hours optimisation
  • A/C RH control optimisation
  • Repair of compressed air leaks
  • Lighting de-lamping
  • Lighting retrofit
  • Metering & demand interval change
  • Remote monitoring


Contact Details

Location of project: Simonstown, Cape Town
Contact person: Mr. C. Wallem (Dept of Public Works)
Telephone: 021 402 2231
Telefax number: 021 419 4099




Other Featured Case Studies

9 Dorp Street, 52kWp Solar PV

9 Dorp Street, 52kWp Solar PV

  • Grid tied 52 kWp roof mounted Solar PV installation
  • SMA inverters
  • Jinko Solar 315Wp polycrystalline modules (oriented North East and North West)
  • Clamped aluminium mounting structure, no roof penetrations
  • Weather station for Performance Ratio calculation
  • 3 year maintenance and performance contract included
Read this case study

VSSC Athlone 109kWp Solar PV

  • Grid tied 109 kWp roof mounted Solar PV installation
  • SMA inverters
  • Jinko Solar 315Wp polycrystalline modules
  • Clamped aluminium mounting structure on atrium and steel structure, no roof penetrations
  • Ballasted mounting structure on flat concrete roofs, no roof penetrations
  • Weather station for Performance Ratio calculation
  • 3 year maintenance and performance contract included